For immediate
release
Feb. 8, 2009
— 10:30 a.m.
Outages
drop under 10,000 for electric cooperatives
Electric cooperatives
fighting to repair storm-ravaged lines reduced the number of outages
to 9,770 Saturday, Feb. 7, as the all-out repair effort continued
without pause. Approximately 2,500 lineworkers are on the ground
in the affected area, which is now confined to southeast Missouri.
Howell-Oregon Electric,
West Plains, is down to just working scattered outages. Their goal
is to finish restoration today.
Ozark Border Electric,
Poplar Bluff, also saw its outage numbers reduced over the weekend.
The cooperative now has 1,840 without power, down from nearly 28,000
at the height of the outage. Manager Stanley Estes says employees
can see the light at the end of the tunnel and are anxious to reach
it.
Hard hit SEMO Electric
Cooperative, Sikeston, saw its outage numbers drop below 2,000 over
the weekend. There are 750 linemen on the ground for the cooperative,
with most focused in the southern Stoddard County area. Very few
if any poles remained standing here in the wake of the storm. SEMO
volunteers made 568 sack lunches for the workers on Saturday.
By far, the worst damage
remains in the two Bootheel counties which are served by Pemiscot-Dunklin
Electric Cooperative, Hayti. On Sunday morning, Manager Charles
Crawford reported that roughly 6,000 members remained without power.
Approximately 900 lineworkers have come to the aid of the cooperative’s
employees, already the largest influx of help ever sent to a Missouri
electric cooperative. Crawford says the cooperative is working on
the logistics of bringing in another 110 workers and has a goal
of more than 1,000 workers.
As the all-out repair
effort continues, power was restored to an additional 100 members
on Saturday, Feb. 7. In addition, the Caruthersville port facility
now has power.
“We added up yesterday,
and the men working have 6,000 poles changed out,” Manager
Charles Crawford said. “We will hit 7,000 without any trouble.”
Progress, measured in
miles of line, continued with another substation south of Portageville
reenergized Saturday. The cooperative now has power to four of its
14 substations, the connection point between M&A Electric Power
Cooperative’s transmission lines and Pemiscot-Dunklin’s
distribution lines.
“We are making
progress,” Crawford said. “We’ve got people just
about everywhere now. Every substation is covered and we’ve
got people in all those new towns we picked up making sure they
are ready when we get power.”
He said repair work is
almost complete in the Maplewood community, with crews finished
changing out broken poles and restringing wire. “We’ve
still got to hook up transformers and services but as far as the
lines go, they are all back up. And it’s moving like that
all across the system.”
With a goal of 1,000
workers assisting the cooperative’s staff, the challenge is
finding housing and meals for this army. Materials continue to pour
into the area and are being spotted in rural areas where they will
be closest to the action.
“It’s
looking a lot better,” Crawford said. “In another week
it’s going to look pretty good. It won’t all be done,
but it will look a lot better.”
-30-
Editor's Note: For media inquiries, contact Jim McCarty at 573-680-2451